Edgemoor's Sewers Run Under Its Backyards. Fixing Them Starts With a Knock on the Door This Fall.

Edgemoor's next eighteen months of change will mostly happen out of sight. The pipes run under backyard lawns, the treatment plant work stays inside a fence at the foot of McKenzie Avenue, and the next round of review for the Woods at Viewcrest sits with state and federal agencies. The City expects to need construction access through about 65 Edgemoor properties. For those owners, the first visible sign is a temporary construction easement, and City staff are setting those up with homeowners this fall.

The herons left the Post Point colony weeks ago and the August appeal calendar has run out, so the neighborhood looks quiet. Underneath, the next phase is already in motion.

The Pipes Behind the Fence Line

On most Bellingham streets, the sewer main runs under the pavement. Edgemoor is different. According to the City's Edgemoor and Columbia Sewer Improvements project page, most of the neighborhood's wastewater lines run through the backyards of homes. That makes them hard to reach for maintenance. Most were installed in the 1950s and are now deteriorating or partly blocked.

The City's own comparison makes the difference clear. The same project covers the Columbia neighborhood, where most of the lines sit in the public right-of-way. There, crews will use conventional open-cut trenching, digging down to the pipe from the street. Edgemoor gets a trenchless method instead, cured-in-place pipe, or CIPP. Crews line the old main from the inside so it doesn't have to be dug up across a row of yards.

The City says putting the work off could lead to major sewer failures and more disruptive emergency repairs.

Here is the scale, as the City lays it out:

  • About 220 properties are affected by the Edgemoor work
  • Crews expect to need construction access through about 65 of them
  • On-site work generally takes one to two days per site once agreements are signed
  • Some spots need digging, either to expose short pipe sections for repair or to install new manholes
  • The City says any disturbed property will be restored to its previous condition or better

Nobody on a crew can walk into a yard without paperwork. The City says temporary construction easements will be signed with property owners before any access is granted. In its Fall 2026 status update, it says staff are establishing those easements now. The City also says staff and contractors will work with owners to find the best access path to each pipe. This post is general information, not legal advice. If an easement request reaches your house, read the City's project page and ask your own attorney what it means for your property.

The Calendar Runs Through 2030

The sewer lining is the job closest to Edgemoor's yards, but it isn't the only work scheduled around the peninsula. The Post Point Resource Recovery Plant at 200 McKenzie Avenue has three projects on overlapping schedules. Read together, they show where the trucks will be and when.

Project Where it stands this fall What the City expects next
Edgemoor sewer lining Easements being signed with homeowners Bids open late 2026, construction summer 2027
Post Point emergency generator Contract awarded Generator delivery and installation start late 2026
Post Point sludge tank replacement Design nearly complete, permitting underway Construction bids advertised late 2026
Post Point emission control upgrades In design, Walsh Construction under contract since September 4, 2026 Construction expected 2027 through 2030

The plant projects follow the same pattern as the sewer work. Both the generator and sludge tank pages say all construction happens inside the plant's fenced perimeter and that no street traffic or public access impacts are expected. Both also say neighbors may see more truck traffic and contractor parking near the facility through 2027. The generators being replaced went in during the early 1990s, and the City says replacement parts are now hard to find.

One part of this work will eventually be visible. The sludge tank project falls under the City's 1% for Art Program, and the money is set aside for art near the Lower Padden trail entrances. The proposal is for art that celebrates Post Point Lagoon and its heron colony.

Viewcrest Left City Hall and Moved Into Agency Files

The Woods at Viewcrest follows the same pattern. Its most public phase, with hearings, packed council chambers and appeal deadlines, is over. What comes next mostly happens in paperwork.

The proposal is a 38-lot subdivision at 352 Viewcrest Road, above the estuary commonly called Mud Bay. Cascadia Daily News reported that Hearing Examiner Sharon Rice approved the preliminary plat, a subdivision variance and critical areas permits in early June. On August 21, the Bellingham City Council affirmed that approval and rejected the appeal from the volunteer group Protect Mud Bay Cliffs. The City's project page notes the council decision was unanimous.

Council member Hannah Stone explained the vote this way, as Cascadia Daily News reported:

"This proceeding is not a vote on whether the council favors the development, nor is it an opportunity for the council to redesign the project or to signal whether it agrees with the concerns the appellant has raised."

The same article notes that a council decision like this one can be appealed to Whatcom County Superior Court through a land-use petition. Protect Mud Bay Cliffs' public update after the vote looks elsewhere. The group says it will keep working with the Washington Department of Ecology, the Washington Department of Fish and Wildlife and the U.S. Army Corps of Engineers, each of which has regulatory authority over parts of the subdivision. It lists stormwater runoff, bluff stability and the public beach below the site as its main concerns.

On the City's side, the Woods at Viewcrest project page lists the remaining steps in order:

  1. Review and approval of the applicant's street vacation petition, covering portions of the unimproved Quinault, 8th, 10th, Fairhaven and Baker Streets in the Amended Map of South Fairhaven Plat
  2. Installation of the required public infrastructure, such as streets and sewer mains
  3. Recording of the final subdivision once all permit conditions are met, which creates the individual lots
  4. Separate building permits for each lot, after which home construction could begin

The plan includes a public trail network connecting the Clarkwood Plat and Viewcrest Road to Sea Pines Road. It does not include public access through the site down to Chuckanut Bay. As of the City's August update, the street vacation was the next listed step. The page gives no hearing date.

The Colony Everyone Is Watching

The Post Point herons nest beside the plant being rebuilt, they are the subject of the art planned for the Lower Padden trail entrances, and they live on the same shoreline Protect Mud Bay Cliffs is focused on.

The City says the Post Point herons typically occupy the colony from February through August. Its latest posted report shows a hard year in 2025: nesting activity fell more than 52 percent and fledglings fell 66 percent compared with 2024. For 2026, the City said it would monitor the Post Point and Little Squalicum colonies together. Results for this season have not been posted yet.

If the herons return on their usual February schedule, the generator installation that starts in late 2026 is expected to be underway at Post Point, and the Edgemoor sewer lining will still be a few months from starting.

Where the Updates Will Come From

Most of this won't show up on the street until it is already underway. The City's Edgemoor sewer page has an email signup for project updates. For Post Point, the generator, sludge tank and emission control pages carry each project's status. For Viewcrest, the City's project page and the Protect Mud Bay Cliffs updates page cover the City and state and federal sides of what happens next.

If an easement request or a crew access plan has you wondering how backyard sewer work fits into selling or holding your Edgemoor home, Julian & Company follows these timelines closely and can walk you through what a 2027 construction schedule could mean for your property. Get your free home valuation and start the conversation.

Work With Us

We pride ourselves in providing personalized solutions that bring our clients closer to their dream properties and enhance their long-term wealth. Contact us today to find out how we can assist you!

Follow Us on Instagram

[ ] Yes, send me marketing text messages. [ ] Yes, I agree to receive non-marketing updates and information such as billing or account updates at the number provided. By clicking one or more of the boxes above and submitting my phone number, I agree to receive text messages from Company Name (DBA - insert if needed) regarding the categories selected above. Message frequency may vary. Message & data rates may apply. Reply STOP to opt out or HELP for help. [privacy policy URL] [SMS T&C URL] Additionally, please ensure the following requirements are met: The checkboxes must remain optional and not required to submit the form Both checkboxes must be unchecked by default